FDOT has proceeded with the selection of a Concessionaire to design, build, finance, operate and maintain (DBFOM) the project through a long-term agreement.
The Concessionaire procurement process will consist of the following phases:
Request for Qualifications (RFQ) advertisement and selection of Short-Listed Proposers (Completed)
Draft Requests for Proposals (RFP) distribution and interaction with Short-Listed Proposers (Completed)
Final RFP distribution (Completed)
RFP Addenda Distribution (On-going)
Short-Listed Proposers submission of detailed proposals
Selection of the Best Value Proposal
Clarifications and execution of the Concession Agreement
The tentative project schedule is as follows:
| Proposal Due Date |
September 5, 2008 |
| Selection of Best Value Proposal |
October 2008 |
| Execution of Contract |
January 2009 |
| Begin Construction |
Summer 2009 |
| Right of Way Clear Date |
October 2010 |
| Construction Complete |
Summer 2014 | Please check back often for updates to the schedule. |  |
|
|
|
|
|
|
|
|